Kwahu East DCE and Monitoring team satisfied with ongoing projects
Kwahu East District Chief Executive, Hon Isaac Agyapong and the District Monitoring and Evaluation Team of the Assembly pleased with the ongoing projects of how steadily the work is progressing.
This came to light after the Assembly conducted a monitoring exercise from 15th to 16th November, 2021 to ascertain the progress of ongoing programmes and projects in the District, to ensure quality assurance and also to ensure value for money in delivery of service.
Ten (10) project sites with funding from DACF, DDF, and GETFUND were visited by the monitoring team.
The monitoring team was led by the District Chief Executive and drawn from a wide spectrum of stakeholders in the District comprising of DPCU Monitoring and Evaluation team, beneficiary institutions, Traditional Authorities, Area Councils/Unit Committee members and other identifiable organizations.
At the time of the visit, most of the projects were at the completion stage. Contractors worked to specification and work output was satisfactory. Materials used were of high quality and met the specification. Those found not to be within specifications were cautioned accordingly.
The team at the time of visit observed that all the contractors had adequate materials on their respective sites and work was progressing steadily. There was adequate labour on each of the project sites.
The monitoring team was satisfied with the type of labour being used by the contractors. However, some of the contractors were not available on site as at the time of visit. The monitoring team was satisfied with the quality of work so far.
Generally, it was observed that work at each of the project site was progressing steadily, contractors were working within the scheduled time and work output was satisfactory. The contractors were urged to work hard to ensure timely completion of the projects.
The monitoring team recommended that completed projects should be commissioned and taken over by the District and there should be provision of fire extinguisher and smoke detectors at projects sites to be commissioned.
The monitoring team also suggested that there should be fencing, landscaping and diversion of road to Bokuruwa CHPS Compound; provision of access road, landscaping and leveling of the building floors of the Mota CHPS Compound and Nkwatia SDA Primary.
In conclusion, the contractors had so far performed creditably and the quality of work was satisfactory. The beneficiary communities have so far been cooperating with the contractors for smooth implementation.
The following projects sites were visited:
- Construction of 1No. 3-Unit Classroom Block with Ancillary Facilities for SDA Primary School.
- Construction of Durbar Grounds at Abene.
- Construction of 1 No. CHPS Compound with Out House at Abisu No.1.
- Construction of 1No. 3-Unit Classroom Block with Offices, Store, 4-Seater KVIP and Urinal at Kwahu-Tafo D/A Primary School.
- Construction of 1 No. CHPS Compound with Out House at Mota.
- Renovation of CHPS Compound and Staff Quarters at Bokuruwa.
- Construction of 12-Seater W/C Toilet at Akwasiho.
- Construction of an Imaging Centre and re-roofing of Bokuruwa CHPs Compound.
- Construction of 1No. 6-unit classroom block with ancillary facilities at Nteso.
- Construction of 14-Seater WC Toilet and Biogas for St. Joseph Technical Institute.
Leave a Reply
Want to join the discussion?Feel free to contribute!